The Tibet Pavilion of 2010 Shanghai Expo will be put into trial operation from April 16 to April 30 as the body construction for Tibet Pavilion was finished on Feb 6.
Currently, the supplementary construction such as pipe-line, fire-control water pipe and concrete pouring is under smooth processing.
As expected, the final preparation for Tibet Pavilion will be completed on March 28 and final debugging will be organized from April 1 to April 15.
Source: China Tibet Information Center